Best Order to Remodel Your Home: Step-by-Step Renovation Guide for Success

Best Order to Remodel Your Home: Step-by-Step Renovation Guide for Success

Imagine this: you’re living in a half-painted house, the kitchen’s gutted, and your living room’s piled with tiles, plasterboard, and a half-drunk mug of tea. That’s the chaos that comes from winging a home remodel without a plan. Sure, it’s tempting to smash out that wall you hate or slap up some fresh paint, but the order you remodel in makes a world of difference. Dive in blind and you’ll spend twice as much money, live in mess for twice as long, and still not get the home you pictured in your head. Surprisingly, a recent UK housing survey pointed out that 60% of home renovators ran over budget—mainly because they messed up the order of works.

Getting Your Priorities Right: What Comes First?

Remodeling isn’t about doing what feels urgent, but about tackling the structural bones before you worry about looks. If your foundation is dodgy or your roof leaks, start there. It sounds boring, but trust me, splurging on fancy kitchens before fixing the roof almost guarantees heartbreak—there’s nothing stylish about water stains and warped cabinets. The general rule: work from the outside in, and from the top down. Repair what keeps the weather out first. Here’s how most pros recommend you line up your jobs:

  • Roof Repairs or Replacement: Even a small leak can destroy ceilings, insulation, and your posh new light fixtures. Get that sorted first. In the UK, more than 80% of property damage insurance claims are water-related. Coincidence? Not a chance.
  • Sorting Foundations and Damp: Manchester’s famously damp, and so are its cellars and ground floors. Before fancying up rooms, deal with damp proofing, foundation cracks, or any shifting that could make your walls crack down the line.
  • Windows, Doors, and External Walls: Drafty windows and crumbly brickwork kill both comfort and energy bills. Swapping out windows and fixing walls early on means you’re not wrecking new plaster or paint later.
  • Structural Alterations: Knocking through for that open plan kitchen? Changing the room layout? That’s next. Doing this after finishing floors or walls will just ruin your new finishes.
  • First Fix Services: This means wiring, plumbing, and HVAC rough-ins go in before you even think about insulation or plastering. Since newer electrical standards came into play in 2022, rewires are especially crucial if your home’s over 30 years old.

Don’t Fall for Quick Fixes: Timing Interior Updates

Once your home is structurally sound and weatherproof, it’s tempting to start painting, laying flooring, or installing your dream kitchen. But there’s a bit more to it. Right after the first fix, you want to put in insulation and tackle soundproofing—no one wants to hear the loo flush from the living room.

Then comes the ‘second fix’: electricians and plumbers finish up, install sockets, switches, and radiators. Then walls and ceilings get replastered, sanded, and generally made pretty. Only after all that should you even think about painting or wallpapering. Floor finishes—especially hardwood or tiles—should be dead last. Why? Even the tidiest contractor manages to scuff things up moving tools or equipment. Save the floor drama for the end.

Remodel StepCommon MistakePro Tip
Heating/AC InstallInstalled after paintAlways before plaster
FlooringLaid before dry trades finishLast job so it’s pristine
Kitchen Fit-OutInstalled before walls finishedAfter decorating, never before
DecoratingEarly, then ruined by tradesmenFinal flourish, never before main works

Ever heard the saying “measure twice, cut once”? Applies just as well to scheduling trades as it does cutting timber. Bodge the order, and you’re inviting chaos. A common pitfall is to redecorate, then realise you need to chase in new sockets or fix a leak behind your kitchen units. Bye-bye, fresh paint.

Planning Like a Pro: Building Your Remodel Timeline

Planning Like a Pro: Building Your Remodel Timeline

Right, so you’ve got big dreams, but how long’s all this going to take? That depends on what you want to change and how many trades you’re juggling. Build your timeline by breaking the remodel into chunks, and leave room for delays. Because, let’s be honest, something always pops up. A typical medium-sized house renovation—think rewiring, altering layouts, new kitchen and bathroom—takes about six to nine months with all trades scheduled tightly. Here’s a rough timeline breakdown for each major task:

  • Structural work / major demolition: 1-2 months
  • First fix electrics/plumbing: 1 month
  • Insulation/dry-lining: 2 weeks
  • Second fix and plastering: 1-3 weeks
  • Decorating (including drying time): 2-4 weeks
  • Flooring fit and joinery: 2 weeks
  • Kitchen install: 1-2 weeks

When making your schedule, double up only where safe—so painting and tiling in the same room? Probably not. But fitting radiators while the tiler is busy in the bathroom? Maybe. Downloading a simple project management app, like Trello or Asana, works wonders for keeping on top of who's doing what, when. And don’t forget to factor in lead times for windows, custom units, or specialty tiles—last year, a surge in home renovations meant some manufacturers had wait times of up to twelve weeks for custom kitchen cabinetry in the UK.

Here’s a bit that most folks forget: apply for all your permits and schedule inspections early. Manchester City Council has an online application, but even so, approvals can drag if you’re changing layouts or utilities. Scrambling for paperwork mid-remodel will stall everything.

Avoiding Budget Blowouts: Where People Go Wrong

Why do folks consistently underestimate the cost and time for a remodel? Usually, it’s because they don’t account for the impact of changing the sequence, or they ignore the domino effect. Change the window sizes after installing plaster? You’ll destroy finished walls and waste money. Order the fancy bathroom tiles late in the game? The plumber and tiler both end up waiting, which stalls your project and often triggers extra charges.

Smart renovators keep a 15-20% contingency fund, just in case things go sideways. The Royal Institution of Chartered Surveyors found that, in 2024, the average home renovation in the UK landed around £68,000, but cost overages hit one in three projects above that number. Main culprits: electrical upgrades, hidden rot, or asbestos. Keep your wallet safe by doing a full survey of the property before even the first swinging hammer.

If your budget’s tight, focus on ‘systems’—plumbing, wiring, heating—first. Splurge on visible finishes only if the house is sound underneath. There’s a myth floating around that tackling each room one at a time is smarter than doing the whole house. In reality, you’ll save on trades and disruption by coordinating big jobs all at once.

Remodel order isn’t just about tidy schedules, it’s about saving money over the long run. Installing underfloor heating? That has to go in before the screed or tile. Want to move radiators? That job is done with first fix plumbing, not as a quick afterthought when the rest is done. It’s worth lining up every wish-list item before you start, so your trades know what’s coming.

DIY or Bring in the Pros? Making It Work for You

DIY or Bring in the Pros? Making It Work for You

The internet’s full of tales about ambitious DIYers gutting their own houses and living through the mess. Sometimes it works, sometimes it’s a saga of stress, dodgy electrics, and civil war with the neighbours. Knocking down a non-load-bearing wall, painting, or fitting skirting boards? Sure, go for it. But if you’re messing with gas, electrics, or major structural changes, always hire qualified tradespeople—UK law’s strict on that, and it’s not worth the risk. In 2023, over 5,000 accidental home fires in England were traced back to unsafe DIY electrical work.

The trick to a great remodel? Know when to step in and when to step back. You can save cash by prepping spaces, managing skips, or sourcing finishes yourself, but never scrimp when it comes to technical jobs. Manchester builders often say the best projects come from clients clear on their priorities, timeline, and budget—but flexible when things don’t go entirely to plan. Trust your gut, but also trust the experts when they push back on your order of works—many have seen it all before.

Lastly, document absolutely everything. Take loads of photos before and after each phase, save all your invoices, and keep a running snag list so you can chase up those little touch-ups at the end. By keeping your eyes on the sequence and planning for hiccups, your remodel might just wrap up on time, under budget, and with your sanity (mostly) intact.